← INSIGHTS

By the Miro3D team · Published

Scan-to-BIM: LOD 100 to 400 explained

What an existing-conditions Revit model contains at LOD 100, 200, 300 and 400, why MEP is scoped on its own, and what to write in your scan-to-BIM RFP.

The short answer

LOD, level of development, describes how much geometry and information each element in a BIM model carries. At LOD 100 an element is a symbol or a mass. At LOD 200 it is a generic placeholder with approximate size and location. At LOD 300 it is a specific, measurable element, and at LOD 400 it carries fabrication-level detail.

For a scan-to-BIM existing-conditions model, the LOD you specify, element by element, decides what you get, how long it takes and what it costs. That is why we quote it rather than publish a price.

Where the LOD definitions come from

Most US teams reference the BIMForum Level of Development Specification. It defines each level by what an element can be relied on for, and gives examples per building element category. It was written mainly for design and construction models, so applying it to existing conditions takes some interpretation: a scanned wall is not a design intent wall, and some information, like the material inside it, cannot be seen.

Some RFPs also cite a separate measured-accuracy standard, such as the USIBD Level of Accuracy (LOA) Specification, which defines accuracy bands for measured data and for the model built from it. LOD says what is modeled. Accuracy says how closely the model has to match the field. Write down both if both matter to you.

What each level typically looks like for existing conditions

LOD 100: building masses, floor levels and overall footprint. Useful for massing, site studies and rough area checks. Rarely worth a scan on its own.

LOD 200: walls with approximate thickness, floors, roofs, openings for doors and windows, stairs and major columns as generic elements in the right place. This is the common starting point for renovation and space planning, and the BIM line on our quote form defaults to this kind of model.

LOD 300: elements modeled at their measured size, shape and location, with specific door and window families, wall types matched to measured thickness, ceilings at measured heights, and key built-ins. It takes more modeling time and expects tighter source data. For large spans or tight tolerances that can mean adding a terrestrial laser scan.

LOD 350: an LOD 300 element plus its interfaces with neighboring systems, such as supports, clearances and connections. BIMForum added it between 300 and 400 for coordination. For existing conditions it only applies where those interfaces are visible.

LOD 400: fabrication and assembly detail. It is rarely appropriate for existing conditions, since you cannot see connections, fasteners or internal layers from a scan. If an RFP asks for LOD 400 existing conditions, it usually means a specific element, not the whole building.

Why MEP is scoped separately

Architectural elements are mostly visible: walls, floors, openings, ceilings. Mechanical, electrical and plumbing systems are often hidden above ceilings, inside walls or in shafts. A scan only records what the sensor can see, so a dropped ceiling hides most of the ductwork and piping.

Where MEP is exposed, as in warehouses, plants and open-ceiling offices, it can be modeled from the scan, but each duct, pipe, conduit and piece of equipment is a lot of modeling time. Listing MEP as its own line, with the systems and the minimum pipe or duct size you care about, keeps the quote honest and keeps you from paying for detail you will not use.

What you get from a Matterport-based scan-to-BIM job

The source capture is a Matterport digital twin, typically delivered 24–48 hrs after capture, plus the E57 point cloud the modeler works from. Matterport depth accuracy is planning-grade, about plus or minus 20 mm at 10 m by Matterport's published specification, which suits architectural existing-conditions models for renovation and planning.

Delivery is a Revit model, or IFC on request, built to the LOD in the quote, in the Revit version and template you specify. The twin stays useful for the whole team as visual context next to the model.

What to put in the RFP

Scope: the buildings, floors and areas, including whether roofs, exteriors, stairs and mechanical rooms are in or out. Disciplines: architecture only, structure, or MEP, with a minimum size for MEP elements.

Level of development per element category, not one number for the whole model. Accuracy expectations, if any. Revit version, template, levels and grids, and whether you need shared coordinates tied to a survey. File formats: RVT, IFC, E57 and the Matterport link. The review process, and who signs off.

An RFP that says only "LOD 300 Revit model of the building" will get very different bids. A one-page table of element categories and levels gets comparable ones.

Frequently asked questions

What LOD do most renovation projects need?

Many architectural renovation projects start with an LOD 200 existing-conditions model, then raise specific elements to LOD 300 where the design touches them. Your architect or BIM manager should make that call.

Is a Matterport point cloud accurate enough for BIM?

For architectural existing conditions at planning-grade accuracy, usually yes. For tight tolerances, structural steel or survey control, add a terrestrial laser scan.

How much does scan-to-BIM cost?

It is custom-quoted. The price depends on building size, LOD and disciplines. The Matterport capture it starts from is published: from $240, which covers spaces up to 2,000 sq ft. Estimates only — every project is custom-quoted.

Is there an LOD 500?

LOD 500 is used in some contracts to mean a field-verified model. The BIMForum specification treats it as field verification rather than a higher level of detail, so it is better to state verification requirements directly.

Can I get IFC instead of Revit?

Yes, when it is specified in the quote. Tell us the IFC version and the software that will open it so the export is checked against that workflow.

Can you model above the ceiling?

Only what is visible. If MEP above a dropped ceiling matters, plan access to lift tiles or scan before the ceiling closes on a construction project.